Sl.No. | Projects in SCP | Cost (Rs. in Crore) | Current Status 30/06/2020 |
| | | |
| Area Based Development (ABD) | | |
| | |
| Taking governance to the neighbourhoods (Multi-Utilities Facilitation Centers – Green buildings | |
| |
| | | |
1 | Dharamnath Circle | 46 | Not Started |
2 | Ramteerth Nagar | 38 | Started |
3 | Mahantesh Nagar | 29 | |
4 | First Rly Gate Opp. Kalamandir | 43 | Started |
5 | Fort Road | 11.4 | Not Started |
| Developing Theme based and heritage Parks & Recreational Spaces | | |
| | | |
6 | Development of a Heritage Park | 26 | Started/ Slow Progress |
7 | Theme-based development/Improvement of Neighborhood Parks & | 15 | Started |
| Recreational Spaces | | |
| | | |
8 | Urban afforeastation through block plantations | 5 | Not Started |
9 | Avenue Plantation | 2 | Not Started |
10 | Art Gallery Cum Exhibition Center and Children Science Park | 14 | Started |
11 | Rehabitilation of Cattle and Pigs | 1 | Cattle Home ready |
12 | Parking forPrivate buses , Mini LCV on Hires charges | 2 | Not Started |
13 | Rain Water Harvesting and composting facilities in parks and | 1 | Not Started |
| gardens | | |
| | | |
| Upgrading of Heritage Precincts | | |
14 | Development of Fort and Moat Precincts | 25 | Not Started |
15 | Improvement of Lakes | 10 | Started |
16 | 24 x 7 Water supply, Smart Metering | | |
16 | Water Metering | 9 | Not Started |
| Enviornment , Energy Efficiency, Renewable Energy | | |
17 | Smart Electricity Metering | 8.5 | Not Started |
18 | Energy Efficiency Program for Street lighting | 5 | Not Started |
19 | UG – LT Cabling | 168 | Started |
20 | Air Quality, Water Quality, Recharge of Water Bodies | 15 | Started |
| Affordable Housing | | |
21 | Development of Affordable Housing for EWS | 84 | Started |
22 | EWS Housing in Approved BUDA Layout | 43.52 | Not Started |
| Skill Development Center | | |
23 | Skill Development Center | 8 | Not Started |
| UG Ducting | | |
24 | Multi-utility UG Ducting | 62 | Started |
| | | |
| Non Motorized Transport,Walkability, Network Connectivity, MLCP, Para Transit | |
25 | Pedestrian friendly Pathways | 45 | Started |
26 | Cycle Tracks | 17 | Started/not one completely ready |
27 | Carriageway Improvement | 125.5 | Started |
| Urban Mobility | | |
28 | Improvement of Central Bus Terminus & City Bus Terminus | 110 | Started |
29 | Flyover | 129 | Not Started |
30 | Underpass | 56 | Started |
31 | ROB | 101 | Not Started |
32 | Improvement of Road Junction Ambience | 4 | Not Started |
| Development of City Centers on Green Building concept | | |
33 | Development of modern market at Tilakwadi (Kalamandir) | 53 | Started |
34 | Development of modern market at Dharamnath Circle | 89 | Not Started |
35 | Swimming Pool and Badminton Court | 3.75 | Not Started |
| Sewerage System | | |
36 | Construction of STP , Uncovered UGD, Improvement/Rehabitilation | 156 | Not Started |
| of sewerage lines | | |
| | | |
| Public Convenience & Amenities | | |
37 | Public Urinals & Toilets | 1.5 | Started |
38 | Road Side Drinking Water Kiosks | 9 | Started |
39 | Bus Shelters | 0.5 | Started |
40 | Tourist Guidance Centers | 3 | Not Started |
41 | Trauma Center (Dharamnath Circle) | 3 | Not Started |
| Solid Waste Management | | |
42 | Solid Waste Management including RDF Plant | 8 | Not Started |
| Storm Water Drain & Recharge of Water Bodies | | |
43 | Primary & Secondary Drains | 70 | |
| ABD | | |
44 | Health (excluded from main proposal of cost Rs. 5 Crores) | | |
45 | Upgradation of Primary Health Centers | | |
| Pan City | | |
| EGOVERNANCE & IT ENABLEMENT | | |
| Central Command Center | | Ready for use |
| Surveillance (GPRS Enabled CMOS Cameras) & Traffic Sensors | | Not Started |
46 | (WVDs) | 12 | |
| Surveillance (GPRS Enabled CMOS Cameras) for Safety security of | | Installed in some places |
| | | |
| Women , Childre and senior citizens & | | |
| Traffic Sensors (WVDs) | | Not Started |
47 | E-Governance (Applications, 3P Services) | 12 | Not Started |
48 | Smart Metering for Electricity | 51.5 | Not Started |
49 | Smart Metering Water Supply | 53 | Not Started |
50 | IT Connectivity | 45 | |
| (Interconnectivity, Kiosks, Wifi & GPRS Subscription) | | Not Started |
| | | |
| Enviornment, Energy Efficiency & Renewable Energy | | |
51 | Solar Rooftop Paneling (30MW) | 195 | Not Started |
52 | Wind Power Generation (30 MW) | 186 | Not Started |